Key ChallengesToad Suck Lock and Dam (also known as Toad Suck Ferry Lock & Dam No. 8) is a key component of the McClellan-Kerr Arkansas River Navigation System (MKARNS), operated by the U.S. Army Corps of Engineers (USACE) Little Rock District. The rehabilitation and painting of 16 large Tainter gates (27 ft high × 60 ft wide) at the Toad Suck Lock & Dam in Conway, Arkansas, presented several challenges.
• Complete removal of an existing lead-based paint system, surface preparation, and application of a USACE-specified vinyl coating system
• Structural repairs (AWS D1.1) including bracing member replacements, deteriorated welded connection repairs, stiffener plate replacements, skin plate repairs, and miscellaneous weld repairs.
• Side seal assembly and j bulb replacement
• Anode replacement
• Reassembly of the Tainter gate hoisting cable hitch block assemblies (including design and installation of temporary gate supports and NDT inspection).
• All work was performed from a floating plant using work barges, with Paragon self-performing stop log installation and removal using company-owned cranes.
Containing the spent abrasive blast media and lead-based paint from these massive gates while maintaining full environmental compliance was critical.
Paragon designed and implemented a state-of-the-art, fully engineered containment system —including the gate arms—that maintained continuous negative pressure and achieved SSPC Class 1A standards. Recognizing the limitations of conventional approaches, we retained an expert professional engineer specializing in industrial abrasive blasting and painting to develop an innovative, custom containment solution specifically for these large Tainter gates.
This new containment system dramatically improved worker safety, ensured complete capture of all spent abrasive and lead-based paint debris, and prevented any environmental release. Our environmental team conducted continuous ambient air monitoring on the adjacent pedestrian bridge and community noise monitoring to ensure zero adverse impact to the public.
The project was completed safely, ahead of schedule, and in full compliance with all environmental regulations and USACE requirements.